Renovation Corner–September 08, 2013

Jan 13Our entrance foyer is now crowded with the massive metal components of an enormous three-dimensional puzzle that will become our elevator! The flooring is being laid in the church this week, including the labyrinth inset—for which a generous donor has stepped forward! The downstairs washrooms are taking shape, along with electrical improvements in the undercroft. The “Creation Space” that will house our Sunday children’s program is beginning to look like a serviceable room and, thanks to another generous donor, the Excellent Adventure will now have furnishings!

Work is now set to begin on the outdoor ramp that will lead up from the outside corner of the church to the Canterbury Room door. That work was held up when we realized that the original plan would have sacrificed the ivy growing on the west side of the church. It was not inexpensive to come up with an alternative plan and then issue a change order, but we felt it was worth it because of the aesthetic value of the ivy.

The new altar, ambo and font are also nearing completion, with a new matching cross, paschal candle and processional torches to be included as part of the package. The drawings were stunning so we cannot wait to see the finished product. The Bishop has been invited to hold several possible dates for the blessing of these sacred items, as is required before they can be put to use.

Renovation Corner–September 01, 2013

Jan 13As the end of the renovations comes into view (giving thanks to God for the absence of dust, noise and inconvenience) we find ourselves facing a Day of Reckoning. How much work remains, and how much money do we have to accomplish it?

The truly amazing fact is that, at every step along the way, as some doors have closed—like the windows we were going cut in the narthex, looking into the church—others have opened—like the sacristy renovations.

But now it also becomes clear that some features of our original plan simply remain out of reach. So our Excellent Adventure program will have a new and improved location (in the old Bethlehem and Nazareth rooms) but it will not have any chairs and tables, sinks or countertops! Similarly our new chapel will not have room dividers to close it off from the main church (though we have a stunning plan that involves some of our old stained glass windows).

If anyone wonders if perhaps our Open Doors campaign (to raise funds for the project) has ended, it has not. It has remained active throughout the renovations for any who want to make a donation toward the project’s completion. And it has never been more necessary than now. Thanks as always for your incredible generosity!

Renovation Corner–August 25, 2013

Jan 13Great progress is being made on our renovations, prompting us to look ahead to issues relating to their completion. The anticipated completion date is now October 13—Thanksgiving!

We are preparing a Donor Appreciation plaque to hang in our narthex. We will be displaying draft copies in the Memorial Hall over the next few weeks and sending out a copy electronically by email. Your help is needed in one of three ways:

  • If      you are a donor, please ensure your name is on the list;
  • if      you are a donor, and your name appears on the list, please confirm the      spelling and any other details;
  • if      you were not a donor, but would like to become one (and have your name on      the list) please make a donation to “St. Stephen’s Church”      (marked “Open Doors Campaign”) by September 15th.

As renovations have continued, a number of features of the original plan have had to be dropped due to budgetary restraints. So we have developed a Wish List of the items that would bring back some of the elements of our original vision. These include (along with an estimated cost):

  • completion      of sacristy renovation (to include washroom): $20,000
  • furniture      for Creation Space (Sunday School & Conference Room): $5,000
  • organ      upgrades: $50,000
  • professional      performance-standard piano: $50,000
  • padded      individual kneeling cushions: $2,500.

If you are interested in donating any of these items, please speak to a member of Corporation or BRAG.

Renovation Corner–August 18, 2013

Jan 13Most weeks meeting for worship down in the lower Memorial Hall seems like a major inconvenience. But it is an excellent opportunity to prepare ourselves for the flexibility the new space will afford us when the renovations are completed upstairs.

When we set up the temporary arrangement in the hall we deliberately chose a semi-circle, with the chairs gathered around the altar and lectern. This allows everyone to be closer to the front, but also closer to one another. It removes the great distance between priest and people that is found in more traditional arrangements. In fact, now the priest sits among the people and simply steps forward to the lectern or altar when it is time to do so.

This arrangement says a number of things about who we are as a faith community. First, it suggests that God is in our midst, rather than somewhere “up there” at the front. Second, it places all God’s people on the same level, as indeed we are. Third, it identifies the entire space—one could say, by extension, the whole world—as sacred and accessible to everyone, not just to a chosen few.

It may appear that we are simply putting in time while updating our worship space. In fact, we are updating the entire way we think about worship. Our temporary set-up downstairs allows us to explore this new understanding and prepare ourselves for taking it with us when we go back upstairs.

Renovation Corner–August 11, 2013

Jan 13Our contractor Karson Builders, has been doing a great job of moving the renovations forward which means that there has been much construction noise, dust and accompanying messiness about our facilities.   Acknowledgments and thanks are extended to Brian, Clara, Lynn, Beverley and Eduardo who have been, and will continue to be, working out of our administrative offices in the midst of the ongoing renovation work.  Anyone who has been through a home renovation knows that it is not an easy thing to live through so many thanks to everyone who spends their days working at St. Stephen’s for continuing to serve the Parish so well during the challenges presented by a renovation project the scope of Open Doors.

The BRAG committee has been discussing a number of exciting design elements for the Narthex and Sanctuary with the hope there will be sufficient funds remaining to permit the realization of these elements.  For example, the pipe organ screens need to be replaced and we hope to create a feature wall to display all of our memorial plaques.  In addition, although the two rear windows between the Nave and the Narthex have been removed from the project, we hope to incorporate a design element by introducing glass panels with decorative screens as entry doors into the Nave. This will allow for the transparency we had hoped for without the cost of the larger windows. We therefore would again like to remind those who have pledges stretching over the next few years to please keep your payments coming.  It is also not too late to provide a new gift to the Open Doors fund, or to sponsor a specific design feature.

Renovation Corner–August 04, 2013

Jan 13Work continues on our renovations at a brisk pace.  The lower level bathrooms are now framed and the fixtures will be on site shortly for our new men’s washroom, women’s washroom and family washroom facilities.

The elevator shaft is close to completion and the elevator will be on site in two weeks time.

As well, the Enmax power service, which incudes a new substation for our expanded power requirements (such as the elevator and the new theatre lighting), will be complete this week.  We are now literally powered for the next 100 years!

More to come!

Renovation Corner–July 28, 2013

Jan 13The installation of the new flooring has been underway this past week.  The Labyrinth piece of the new flooring has been ordered and will be installed in the main floor area of the Nave.  As well, one bank of the new theatre lighting is now in place in the ceiling of the Nave, with the two remaining banks to be installed shortly.

As last reported, BRAG had been concerned about a delay of potentially a considerable amount of time in the Enmax work due to the Calgary flooding (which would have then delayed a number of other elements of the renovations).  While flooding issues in Calgary did result in some delay in Enmax being able to get to the work at St. Stephen’s, BRAG is pleased to report that Enmax has now commenced work at St. Stephen’s.

Although not the most glamorous part of the project, our expanded sewer facilities are now in place and work is proceeding full speed ahead on the new lower level washrooms.  More to come on the progress on the washrooms and other lower level elements of the project in the coming weeks.

Renovation Corner–August 11, 2013

Jan 13Our contractor Karson Builders, has been doing a great job of moving the renovations forward which means that there has been much construction noise, dust and accompanying messiness about our facilities.   Acknowledgments and thanks are extended to Brian, Clara, Lynn, Beverley and Eduardo who have been, and will continue to be, working out of our administrative offices in the midst of the ongoing renovation work.  Anyone who has been through a home renovation knows that it is not an easy thing to live through so many thanks to everyone who spends their days working at St. Stephen’s for continuing to serve the Parish so well during the challenges presented by a renovation project the scope of Open Doors.

The BRAG committee has been discussing a number of exciting design elements for the Narthex and Sanctuary with the hope there will be sufficient funds remaining to permit the realization of these elements.  For example, the pipe organ screens need to be replaced and we hope to create a feature wall to display all of our memorial plaques.  In addition, although the two rear windows between the Nave and the Narthex have been removed from the project, we hope to incorporate a design element by introducing glass panels with decorative screens as entry doors into the Nave. This will allow for the transparency we had hoped for without the cost of the larger windows. We therefore would again like to remind those who have pledges stretching over the next few years to please keep your payments coming.  It is also not too late to provide a new gift to the Open Doors fund, or to sponsor a specific design feature.

Renovation Corner–August 04, 2013

Jan 13Work continues on our renovations at a brisk pace.  The lower level bathrooms are now framed and the fixtures will be on site shortly for our new men’s washroom, women’s washroom and family washroom facilities.

The elevator shaft is close to completion and the elevator will be on site in two weeks time.

As well, the Enmax power service, which incudes a new substation for our expanded power requirements (such as the elevator and the new theatre lighting), will be complete this week.  We are now literally powered for the next 100 years!

More to come!

Renovation Corner–July 28, 2013

Jan 13The installation of the new flooring has been underway this past week.  The Labyrinth piece of the new flooring has been ordered and will be installed in the main floor area of the Nave.  As well, one bank of the new theatre lighting is now in place in the ceiling of the Nave, with the two remaining banks to be installed shortly.

As last reported, BRAG had been concerned about a delay of potentially a considerable amount of time in the Enmax work due to the Calgary flooding (which would have then delayed a number of other elements of the renovations).  While flooding issues in Calgary did result in some delay in Enmax being able to get to the work at St. Stephen’s, BRAG is pleased to report that Enmax has now commenced work at St. Stephen’s.

Although not the most glamorous part of the project, our expanded sewer facilities are now in place and work is proceeding full speed ahead on the new lower level washrooms.  More to come on the progress on the washrooms and other lower level elements of the project in the coming weeks.